Bob Aaron bob@aaron.ca
January 26, 2008
Is secrecy a major structural defect in buyer protection?
How will buyers of new homes in Ontario know the meaning of a “major structural defect” under the Tarion warranty if the corporation imposes a gag agreement on settlements of lawsuits against it?
That’s the question after a secret resolution of claim brought by Tim Fuller and Patricia Swick, who bought an Ottawa townhouse in 1998 and spent nine years battling the builder and Tarion Warranty Corp. over outstanding issues.
Under the Tarion program, a house is guaranteed to be free from major structural defects (MSDs) for seven years after possession. Within that time limit, Fuller and Swick submitted a number of MSD claims to Tarion, and all were rejected. They appealed Tarion’s decision to the Licence Appeal Tribunal (LAT) in 2006 and their claims were again tossed out.
Unhappy with the LAT decision, the couple retained Ottawa lawyer Christopher Arnold to launch an appeal to the Divisional Court. The case involved key issues surrounding the definition of an MSD, and some industry stakeholders eagerly awaited the ruling.
Suddenly, about a week before the court hearing and nine years after the house was purchased the case was quietly settled and disappeared from the court docket. When I tried to find out how it had been resolved, I was told by all parties the settlement was subject to a “will not disclose” agreement.
According to Tarion’s governing regulations, an MSD is defined as a defect in work or materials that materially or adversely affects the load-bearing function of a building.
In its Fuller and Swick decision, however, the LAT appears to have re-interpreted that regulation to add an additional requirement that the defect “should be” one that renders a home “virtually uninhabitable … unsafe, or in a state of imminent collapse.”
Arnold, representing Fuller and Swick, believes the LAT was wrong and cited a 1997 court decision in the Grudzinski case, which supports his position, he says. The “imminent collapse” test, he told me last week, is not and never has been part of the Tarion legislation, and shouldn’t form any part of how Tarion defines what is and what is not a MSD.”
The Fuller and Swick appeal hinged on four issues the couple claimed were MSDs. Basically, the claims were that load-bearing columns, posts or walls on the main floor were not aligned with or not properly secured to structural supports below. But since the settlement is secret, we will never know how the issue of the MSDs was resolved despite considerable public interest in the issue.
A Tarion spokesman told me this month the non-disclosure term in the settlement was imposed by Tarion “to avoid confusion with others who have different circumstances from assuming that they would be entitled to identical settlement agreements. … each file is dependent on its own facts.”
Frankly, to say that present or future litigants would be confused if the Fuller and Swick settlement was made public insults the intelligence of others involved in claims against Tarion.
The outcome of all Tarion’s proceedings and settlements should be public. The program should operate in an open and transparent manner; its culture of secrecy is clearly not in the public interest.
Unfortunately, the public record on the Tarion website records only the “imminent collapse” definition of MSD in the Fuller and Swick case, although my guess is that Tarion backed away from that interpretation with a considerable cash payment to the homeowners.
Marek Tufman is a senior Toronto litigator who represented the successful claimants in the 1997 Grudzinski case, which also involved the definition of an MSD. This week, he told me that although the warranty corporation is entitled by law to impose a gag order, a public statutory body like Tarion “should not maintain a cloak of secrecy over this type of arrangement.” There is a substantial public interest in this issue, he added.
Meanwhile, Linda Williamson, communications manager for the provincial Ombudsman’s office, told me the Ombudsman does not have jurisdiction over Tarion. The office, however, is assessing complaints it has received in order to determine whether an investigation is warranted into the degree of protection that Ontario offers to new homeowners.
Bob Aaron is a Toronto real estate lawyer. He can be reached by email at bob@aaron.ca, phone 416-364-9366 or fax 416-364-3818. Visit the column archives at www.aaron.ca/columns/toronto-star-index.htm.
http://www.lat.gov.on.ca/english/decisions/2006/ONHWPA/Aug/3409.onhwpa.fuller.swick.pdf
Licence Appeal Tribunal
TIMOTHY FULLER AND PATRICIA SWICK
APPEAL FROM A DECISION OF THE CORPORATION
DESIGNATED FOR THE PURPOSES OF THE ONTARIO NEW
HOME WARRANTIES PLAN ACT
TO DISALLOW A CLAIM
TRIBUNAL: DANIEL LAURIN, Vice-Chair
APPEARANCES: TIMOTHY FULLER AND PATRICIA SWICK, Applicants, appearing
on their own behalf
DANIEL BOIVIN, Counsel, representing Tarion Warranty Corporation
DATES OF HEARING: June 14-15, 2006 Ottawa
REASONS FOR DECISION AND ORDER
BACKGROUND:
Timothy Fuller and Patricia Swick (the .Applicants.) took possession of a dwelling located
in Ottawa, Ontario on September 04, 1998. The dwelling is a town house. From a block of
seven, it is the first unit on the left. It is identified as block 5.
The Applicants provided notice of their claims to Tarion Warranty Corporation (.Tarion.)
on August 26, 2005, in relation to 12 specific items, that reads as follows:
1. Structural deficiencies / load bearing column on the main floor does not align with the
structural support below the floor. This is causing a significant distortion in the main floor.
2. Structural deficiencies / wood beam at dropped foyer has been notched 1/3 over the
support. This beam should be reviewed to determine if the remaining portion of the beam is
capable of supporting all specified loads.
3. Structural deficiencies / steel tele-post is not properly secured to the floor…
4. Structural deficiencies / questionable support for load bearing column at the end of the wall
between the living room and kitchen. Drawings require double (2-ply) 2 x 10 beams, Trust
Joist layout indicates (2) 1-3/4 x 9 LVL beams, and the actual installation is a single LVB
beam. A built up wood column and added footing is provided at that location, however,
blocking in the ground floor joist may not be adequate.
5. Structural deficiencies / anchor bolts to the foundation are not visible at the garage wall.
6. Fire separation issues (in garage) / large gaps in gypsum board.
7. Fire separation issues (in garage) / improperly sealed joints in gypsum board.
8. Cladding issues / deficiencies with brick veneer; improperly installed or missing through-wall
flashing at the foundation.
9. Moisture issues / effloresce on the foundation wall in garage.
10. Moisture issues / staining of drywall in garage.
11. Moisture issues / staining of frame around the window in the master bedroom.
12. Plumbing issues / hammering identified in home.
Tarion inspected the dwelling on January 4, 2006. Tarion issued a decision letter dated
January 19, 2006, in which all the claims were denied since they were considered as not
constituting a major structural defect, as defined in section 1 of Regulation 892 of the Act.
Tarion indicated that there was no defect in work or materials, which has resulted in the
failure of any load-bearing portion of the building, or a condition which materially and
adversely affects its load bearing function. The Applicants filed a Notice of Appeal with the
Licence Appeal Tribunal that was received on February 08, 2006.
PREHEARING:
No pre-hearing took place.
That is where the Tribunal was on the day of the hearing.
WITHDRAWAL AT HEARING:
At the start of the hearing, the Applicants told the Tribunal that they did not want to
proceed with item numbers 9, 10 and 12. The Tribunal was then left with items 1, 2, 3, 4,
5, 6, 7, 8, and 11 to adjudicate.
EXHIBITS:
Eight (8) exhibits were filed with the Tribunal:
1. Decision letter dated January 19, 2006 issued by Tarion Warranty Corporation.
2. Notice of Appeal form filed by the Applicants and received at the Tribunal on
February 8th, 2006.
3. Applicant.s Book of Documents Volume I.
4. Applicant s Book of Documents Volume II.
5. Engineering reports prepared for the Applicants.
6. Respondent.s Book of Documents.
7. Document from the Applicants in relation to the definition of major structural defect.
8. Respondent s Book of Authorities.
EXPERT WITNESSES:
The Tribunal did not conduct a .voir-dire. since both parties were satisfied with the
qualification of both expert witnesses in the present case.
THE EVIDENCE:
Witnesses for the Applicants
1. Timothy Fuller
The witness is one of the Applicants. He described to the Tribunal the problems they
encountered and gave his opinion about the state of the major structural defects in their
home and the other complaints. In his opinion, it was covered by the 7-year warranty,
since the load bearing was seriously affected. As per the non structural items, he basically
started to repeat what was in the report of his expert witness. At that point the Tribunal
intervened and asked the witness to let his expert testify about these items. The witness
agreed and continued his testimony.
He was contacted by the builder on December 4th, 2005 (Joe Marshall, Ashcroft s General
Construction Manager) Ashcroft asked for an appointment even though Ashcroft had no
jurisdiction in the matter; he was interested to see the problems since if the home was
afflicted with major structural defects it would have by definition, failed (in Mr. Marshall s
opinion). The witness felt he was not obliged to meet with the builder and declined the
offer.
The witness told the Tribunal that they have suffered damages. The estimation of all the
work to be done is included in their second expert report.
They see their home as an investment and by law they are obliged to report deficiencies
to potential buyers before selling it, hence having to bear the brunt of the cost of the
repairs.
They are not happy to live around their deficiencies problems.
The Tribunal asked the witness if one of his complaints #50 (Structural Anomaly .
Basement) contained in a previous decision of this Tribunal Timothy Fuller and Patricia
Swick (February 25, 2002) was the same that he was bringing back at the present
hearing:
At page 9 of the decision:
#50 Structural anomaly . Basement (number taken from Conciliation Report)
This claim involves a footing pad supporting an upright beam shown in Exhibit # 8, photo
12. Proof of the Applicant s claim would require evidence from an expert. Mr. Fuller
indicated that at this time he did not want to pursue this further. The Applicants not
proceeding with this claim, the Applicant s claim is denied.
The witness answered in the positive.
In cross-examination the witness told the Tribunal that he was not an engineer. He was
not qualified to say if a building would collapse or not. He possesses no professional
knowledge in the building industry. He told the Tribunal that he was able to use every
room in the house on the 2 floors and had full use of his basement, and that it was fully
used since the date of possession. When he realized in the spring of 2004 that there was
a bump in his floor he did not notify Tarion or his builder. He obtained an expert report in
July of 2004 but did not communicate it to Tarion until May 2006.
2. Alasdair Higginson
The witness is a structural engineer and building science professional with the firm of
consulting engineers, Buchan, Lawton, Parent Ltd of Ottawa, Ontario. He possesses 10
years of experience conducting structural investigations. He received a B. Eng at Carleton
University in civil engineering in 1996.
The witness had produced 2 different engineering reports one dated July 16, 2004 and the
second one dated May 11, 2006. Both reports were requested by the Applicants. The
witness testified that he noted problems on his first inspection on May 19 2004 that he
classified as follows:
Structural deficiencies:
The witness told the Tribunal that architectural drawings showing the framing layout for
the home and trust joist framing plan were provided by the owner for review.
He noted that the load bearing column on the main floor, supporting loads from the
second floor, is not properly aligned with the structural supporting members below the
ground floor framing. (wood blocking, steel beam and steel telepost) The offset of this load
has caused a significant bump in the main floor over the wood blocking and the floor
sheathing is separating from the floor joists. Since the load is not properly transferred to
the steel beam and telepost, it appears to be loading an unsheathed wood stud wall and
causing the studs to buckle. Proper support for this column must be provided.
The wood beam at the dropped foyer floor has the top 1/3 notched over the support. This
beam should be reviewed to determine if the portion of beam remaining has sufficient
strength to support all specified loads. There are teleposts that are not properly secured to
the floor. Questionable support for load bearing column exists at interior end of wall
between kitchen and living room. Architectural drawings indicate double 2-ply 2 x 10
beams. Trust joist layout indicates 2 . 1 3/4 x 9 1/2 LVL beams, and actual installation is a
single LVL beam. A built up wood column and added footing is provided at that location,
however, blocking in the ground floor joist space may not be adequate. Finally, anchor
bolts to foundation are not visible at the garage walls.
Fire separation issues in the garage:
There are large gaps and openings in gypsum board. Also there are improperly sealed
joints in gypsum board.
Cladding issues:
Deficiencies were noted with the brick veneer, including it was improperly installed or
missing through-wall flashing at the foundation wall and shelf angles.
He concluded in the summer of 2004 that all issues required further investigation to
determine the full extent of deficiency involved and to devise an appropriate remedial plan.
Second Report
Furthermore he testified that he revisited the dwelling in the spring of 2006 and provided a
second more detailed report dated May 11, 2006. His conclusions were basically the
same with more details and proposals on how to fix the problems identified. He also
provided an estimate of the costs of the repairs:
For structural repair costs:
Improperly supported ground floor column: $ 1500.00
Notched wood beam below dropped foyer floor: no cost
Improperly secured steel teleposts: $ 300.00
Improperly supported ground floor wall and column: $ 1600.00
Anchor bolts to foundation wall (assume 10 bolts) $ 650.00
________
For a total of $ 4050.00
He also provided an estimate for non-structural issues as follow:
Fire separation issues – Seal gap in the fire separation at the garage roof $ 500.00
Cladding issues . Install proper through-wall flashing $ 2000.00
Moisture issues . further investigation
________
For a total of $ 2500.00
In cross-examination the witness admitted that despite his observations to the effect that
some of the complaints did not meet the Building Code Specifications, in his opinion, he
was unable to find any evidence that the load bearing of the house was affected or that
there was any failure of column or supporting walls. Furthermore, he was unable to say if
the anchor bolts in the garage were missing, or camouflaged by a second structure added
during construction on the first one. He was unable to say if any of the structures will fall or
not.
He also agrees with the Counsel for the Respondent that transfer of weight to a post that it
initially was not supposed to support does not change the fact that it is still supported and
that the load bearing of the structure is not affected.
Witnesses for the Respondent
3. Robert Fisher
The witness is currently employed by Tarion Warranty Corporation as a field claims
representative. He had previously worked in the engineering field of designing optical
telephone equipment (optical division).
He performed the inspection of the dwelling on December 1, 2005 and filed a report of his
findings on January 18, 2006.
His detailed warranty assessment report said that he did not notice any load-bearing
support structure problems and no evidence of defects in work or material that adversely
affects the use of the home for which it was intended.
In relation to complaint number 1, the witness said that the homeowner clarified his
complaint as being a concern of the supporting structure under the specified area. The
area in question is supported by various wood beams and associated floor joists, which
are in turn supported by wood framed walls. In relation to complaint number 2, there was
no noticeable downward deflection of the beam when viewed from the basement area and
the floor area above the beam displayed no noticeable bounce when walked on.
Regarding complaint number 3, the jack post in question was checked with a four-foot
level and found to be plumb in both the north-south plane and the east-west plane. The
top of the jack post is secured to the metal I beam and the base of the jack post rests on
the concrete basement floor slab and is not fastened to the floor. In relation to complaint
number 4, the floor joist above the middle basement wall was not observed to be distorted
in any way and the groupings of five 2×4 supports were observed to be firmly and securely
in place with no noticeable bowing. The second floor area directly above this area was
observed and no cracks in the drywall were noticed. In addition, the living room hardwood
floor immediately adjacent to and east of the fireplace, located on the main floor of the
living room, was found to be sloping towards the hallway. The living room area above the
floor joist in question displayed no noticeable bounce when walked on.
With item complaint 5, the east side of the garage wall is finished with drywall and, as
such, the existence or non-existence of anchor bolts could not be determined in this area.
The west side of the garage was viewed and no protruding anchor bolts were observed.
Anchor bolts may exist below the top 2×4 on the garage sill and as such could not be
viewed. No evidence of movement of the garage walls relative to the foundation was
observed. In relation to complaint number 6, small cracks in some of the joints between
the drywall sheets in the garage were observed, which are typical or normal shrinkage of
materials. As per complaint number 7, the drywall joints to the roof peak wood sheeting
areas were observed to not be caulked. Complaint number 8, no defect with the brick
cladding was observed. As per complaint 11, there is no water penetration at this point,
just a small stain approximately one inch in diameter over the east master bedroom
window.
(Complaints 9 -10 and 12 were withdrawn)
In his opinion none of these nine (9) items of complaint constitutes a major structural
defect.
In cross-examination he told the Tribunal that he had inspected about 50 homes before
showing up at the Applicants dwelling. All the reports are reviewed by senior personnel at
Tarion before being released.
4. Vincent Ferraro
The witness is a member of Daley Ferraro Associates, Engineering Services situated in
Ottawa, Ontario. He received a Bachelor of Civil Engineering & Engineering Mechanics
from McGill University in 1979, as well as a Master of Engineering, Specialty in Structures
and Micro-Climate Engineering, from the University of Western Ontario in 1984. He is a
member of Professional Engineering Associations in Ontario, Quebec and Nova Scotia
and also a member of IABASE. (International Association for Bridge and Structural
Engineering)
The witness visited the dwelling owned by the Applicants on May 12, 2006. He followed
the items of complaint submitted by the Applicants and after a thorough investigation
reached the following observations and conclusions:
Observations
The residence under investigation is a seven-year old two-story dwelling with a partially
finished basement. The structure is comprised of typical wood framing supported on a
poured concrete foundation. Floor joists and floor beams, as viewed from the basement
area, are part of the .Silent Floor. system produced by Trust Joist MacMillan. Various
beams are of the .Timberstrand LSL. variety. The house is an end unit of a townhouse
row of seven.
The building contains structural and non-structural deficiencies.
The structural deficiencies are:
1. Column misalignment near entrance (Main floor to basement)
The main floor column was observed to be misaligned relative to the steel telepost in the
basement by approximately one foot. In an attempt to compensate, the contractor installed
a stub column between the top of the beam in the basement and the floor sheathing. This
attempt is without merit and is in fact harmful, as it places stresses on the floor sheathing,
which it cannot take. In addition the steel basement column is not fixed at its base, and
was installed after the concrete floor was poured. This also raises the concern that there
may not be a footing beneath it. Column misalignment and lack of fixity are a structural
deficiency according to the Ontario Building Code (OBC 1995) and lack of proper footings
would also be considered as such. However, this is nothing major. There is no significant
movement or damages. The condition of the floors and the basement are proof of that.
There is no failure of weight bearing capacity.
2. Notched wood beam below entrance foyer
The wood beam below the entrance is a twin 9 1/2 by 1 3/4 Timberstrand LSL Beam,
which primarily supports second floor elements. The beam has been notched to
approximately 2/3 of its depth 6 1/2. Calculations indicate that while it is not desirable, it
remains adequate to support the applied load. Therefore the beam is not defective for this
reason. However, we noted as a separate item that the beam bears on the opposite
concrete wall by 1 . According to the building code, the minimum bearing for beams
shall be 3 (Section 9.23.8.2) Manufacturer s specifications call for a minimum bearing of
2 . Therefore, the beam bearing is considered to be a structural defect. However, there
is currently no damage associated with this deficiency. It is not a major structural
deficiency. There is no sign of failure or imminent failure.
3. Steel telepost not secured to floor
This issue has been discussed in complaint number 1.
4. Support beneath wall separating kitchen & living room
The wall separating the kitchen from the living room is supported on a single 9 x 1
LSL beam, which in turn is supported at mid span by a retrofit wood column with an
intermediate eccentric stub column. We understand that the original design called for twin
LSL 9 x 1 beams at this location. Based on the fact that the LSL beam is supported
near mid-length means that its capacity is not in question. However the eccentric and
imperfect support is contrary to building code requirement. (OBC Sections 9.23.8.3,
(.23.9.8 (4)) As such the eccentric support represents a structural deficiency which should
be corrected. However, except for the floor bowing seen by the fireplace on the main floor,
there are no current structural damages arising from this deficiency. It was noted also that
the wood column supporting the LSL beam was a retrofit column with retrofit footing
installed by the contractor after a larger deficiency was discovered by the city inspector.
These 4 complaints have not resulted in reduced load carrying capacity of the foundation
system at the current time. The presence of these deficiencies has not adversely affected
the use of the building for its intended purposes to the present. However, despite current
conditions, the structural deficiencies represent weaknesses in the structure that will likely
cause accelerated deterioration and future problems.
The non .structural deficiencies are:
05. Non-visible anchor bolts in garage
Only one anchor bolt was seen in the garage. While they may be hidden and present, the
building code requires that they be installed at a spacing of 7.6. (OBC Section 9.3.6(2)
and (3)) However it is not a structural deficiency resulting in damage to this point. No
shifting, no lateral shifting from the inside and no brick cracks from the outside were
noticed.
06. Gaps in drywall between units
The OBC requires construction of a one-hour fire separation between residential suites
(OBC Section 9.10.9.11) The presence of penetrations across the gypsum board in the
garage represents weaknesses in the fire wall, which must be sealed to control fire
passage. This is a building envelope infraction. This is nothing major and has no bearing
on the capacity of roof trusses.
07. Gap in drywall Flashing
Same comments as above with complaint number 06.
08. Through-wall flashing
The brick masonry wall along the front walkway was seen to have adequate weep holes.
While we could not see the through-wall flashing, which is required by the building code to
extend beyond the brick (OBC Section 9.20.13.6(1), there is no evidence of water entry on
the garage side of the wall or other water related damage. We would have seen water
penetration and deterioration of wood and masonry if it had been the case. While this may
be a code deficiency (we could not see the through-wall flashing which is required to
extend beyond the brick) there have been no consequences to this date and will likely not
be any in the future, presuming the flashing is present but not visible.
09. Effloresce on Foundation wall by garage
10. Drywall stain in garage
12. Plumbing noises
(withdrawn)
11. Water stains around master bedroom window
Several small water spots were observed on the inside soffit surface of a window frame in
the master bedroom. A small amount of water entered through the building and roof
interface, probably due to ice damming during the wintertime. This appears to be an
isolated event not associated with a building deficiency.
These non structural deficiencies have not diminished the load carrying capacity of the
structure nor the intended use of the building.
AUTHORITIES:
The Respondent filed a book of authorities received in evidence as Exhibit 8.
That book contained several cases. The cited cases were:
Re McGlade (August 11, 2003), (L.A.T.)
The Tribunal said at page 11:
Many homeowners are not aware of the burden of proof that they must satisfy in order to
meet the definition of major structural defect as stated in Regulation 892. This definition is
quite restrictive. Either there must be a failure of the load bearing portion of the building or
the building cannot be used for its intended purposes. As has been illustrated by the
caselaw this warranty was intended to deal with extremely serious problems of construction,
which can take place over a lengthy period of time. The legislature has permitted
homeowners to have a long warranty period of seven years as it is recognized that major
structural defects might either not happen immediately upon possession of a home or might
develop slowly over time.
Re Kennedy (July 16, 1982), (C.R.A.T.)
The Tribunal said at page 110:
A major structural defect in our view and as we have found in the past must inter alia, be
one which renders a home virtually uninhabitable, uncomfortable beyond reason, unsafe or
in a state of imminent collapse.
Re Fields (October 21, 1982), (C.R.A.T.)
The Tribunal said at page 92:
The use of the word .major. in the all-important phrase .major structural defect., which was
devised by the Legislature in its wisdom when it framed this Statute, was almost certainly
deliberate. Without it we are left with two words only viz. .structural defect . and the
warranty would apply to anything qualifying for that bare definition. But it doesn.t, because
the Legislature has used the word .major.. The defect must therefore be .major. to be
warranted. In this case that has not been proven, although the onus is very clearly upon a
claimant to do so in order to succeed.
Re Allan, {1999} O.C.R.A.T.D. No.7
The Tribunal said at paragraph 31:
The possible lateral flexing of the steel I-beam described in Claim # 20 is not a major
structural defect according to the definition of a major structural defect in Regulations. In the
case of Galko {1994} CRAT this Tribunal considered what would amount to a major
structural defect. .Major. was compared to .minor. and the conclusion was that the defect
must be one that renders a home virtually uninhabitable, uncomfortable beyond reason,
unsafe or in a state of imminent collapse. None of these standards apply here and there
was nothing visibly wrong.
Re Lowry, {1999} O.C.R.A.T.D. No. 256
The Tribunal said at page 15, Paragraph 97-98 and 99:
97. In Pengelly (1995) O.C.R.A.T. No. 60 this Tribunal considered the issue of potential
future problems. At paragraph 16 the Tribunal states:
.The Angelo Proestos (1992) CRAT 758 and Dan Vera (1988) 17 CRAT 185 cases
established that a fear of future potential problems cannot constitute a major
structural defect..
98. This principle was more recently affirmed by this Tribunal in the Mark and Lynne Allan
case released in January 1999. The Tribunal found at page 7:
Mr. Baxter testified that the problem is that the studs behind the brick would rot in time. At
the most, this is a problem that could arise in the future. Two cases establish that fear of
future problems cannot constitute a major structural defect, Proestos (1992) CRAT 758 and
Dan Vera (1988) 17 CRAT 185.
99. The Tribunal notes that in the Allan case the Tribunal found that a steel beam was not
anchored and presented a danger of considerable magnitude that was clearly a major
structural defect. The Tribunal found that the beam was unsafe and adversely affected the
load-bearing function of the house. However, in the case now before this Tribunal, there is
insufficient evidence of any major structural defect, and there is no evidence of any
imminent . danger of considerable magnitude..
Re Pergunas, {2002} O.L.A.T.D. No. 294
The Tribunal said at paragraph 66, 67 and 68:
66. Counsel for the Program states that the onus is on the Applicant to show the problem
meets the definition of major structural defect. After reiteration of the evidence Counsel
directed the Tribunal to a number of cases.
67. In the case of Galko {1997} O.C.R.A.T.D. No. 111 there is a discussion of the concept of
major structural defect. It is stated at page 3 .A major structural defect in our view and as
we have found in the past must inter alia be one which renders a home virtually
uninhabitable, uncomfortable beyond reason, unsafe or in a state of imminent collapse..
68. In the case of Re Buss O.C.R.A.T.D. No. 257 it is stated that prospective fears do not
make a defect a major structural defect. In the case of Lowry O.C.R.A.T.D. No. 256 the
Tribunal quotes two cases Proestos (1992) CRAT 758 and Dan Vera (1988) 17 CRAT 185
for the proposition that fear of future problems cannot constitute a major structural defect. In
the case of Re Restagno O.C.R.A.T.D. No. 129 the Tribunal found that there was no major
structural defect as there was .no failure to any load bearing portions or any major negative
impact on its load bearing function. . The use of the building was not materially and
adversely affected.
Re Mazza (October 7, 2003), (L.A.T.)
The Tribunal said at page 24:
The Tribunal in Ban characterized the Applicants evidence as follows:
The comments by Mr. Wong and the Applicants are speculative in nature and are
directed to a situation which could develop at some point in the future if the repairs
are not effected. The Tribunal cannot take such speculation into account when
making a determination on whether or not there is a major structural defect in a
home. (emphasis added)(at page 14)
There is little difference in the present case. The Mazza home, it was agreed by all,
has not fallen down and the foundation is presently supporting the loads of the
home. There has been no shear failure. There are no observed horizontal cracks in
the foundation also accompanied by foundation displacement. In fact, the basement
is mostly finished and is used by the Mazzas as a living place.
Tribunal
The Tribunal did its own research and the leading case of Kennedy (1982) 11 CRAT 109
has set the standard which has been followed to date, and that is:
A major structural defect in our view and as we have found in the past must inter alia be
one, which renders a home virtually uninhabitable, uncomfortable beyond reason, unsafe or
in a state of imminent collapse.
Also in the same year, the case of Dr. Louis Fields (1982) CRAT Volume 11, p.88 at p.92
and 93 dealt with the term .major. with respect to structural defects and held as follows:
The use of the word .major. in the all important phrase major structural defect, which was
devised by the Legislature in its wisdom when it framed the Statute, was almost certainly
deliberate. Without it we are left with two words only viz. .structural defect. and the warranty
would apply to anything qualifying for that bare definition. But it doesn.t, because the
Legislature has used the word .major.. The defect must therefore be .major. to be
warranted. In this case that has not been proven, although the onus is very clearly upon a
claimant to do so in order to succeed.
and later:
In passing the Tribunal notes that the use of the word .major. implies the fact that there
exists an antonym to that word or complementary opposite which is the word .minor.. That
is to say, the concept of a .major structural defect. implies the complementary concept of a
.minor structural defect.. The Legislature must have had both such kinds of deficiencies in
contemplation . one warranted and one not warranted.
In the case of McArthur (1989) CRAT 213, a defect complained of was of certain problems
with the windows which were not closing properly as well as the bowing of exterior metal
sills. This was the result of a differential movement between the wood frame wall and the
brick veneer, which was caused by the shrinkage of the wood framing. The former New
Home Warranty Program accepted that this was a structural defect, but not a major
structural defect. In this case, it was proven that the structural integrity of the home was in
no way threatened by the shrinkage.
At page 216:
The defects in the structure through shrinkage can be characterized as a structural defect.
The question is, however, is this structural defect a major one and therefore subject to the
four-year warranty? The Tribunal believes it is not because the home is suitable for living and
the owners have made full use of it.
The decision of Donald and Belle Murchie (LAT 2004) written by Vice-Chair Jane Weary
should apply in the present hearing:
She wrote at page 10:
To support their claim for warranty under the Act, the Applicants are required to establish that
their home has major structural defects as such are defined in the Act in Regulation 892. As
has been noted in countless prior decisions of this Tribunal, many owners simply fail to inform
themselves of the restrictive case they are required to meet under the legislative definition of
.major structural defect ..
In McGlade (LAT 2003) Ms. Hiley, Vice-Chair of the Tribunal, stated at page 11:
Many homeowners are not aware of the burden of proof they must satisfy in order to meet
the definition of major structural defect as stated in Regulation 892. This definition is quite
restrictive. Either there must be a failure of the load-bearing portion of the building or the
building cannot be used for its intended purposes. As has been illustrated by the case law
this warranty was intended to deal with extremely serious problems of construction, which
can take place over a lengthy period of time. The legislature has permitted homeowners to
have a long warranty period of seven years as its recognized that major structural defects
might either not happen immediately upon possession of a home or might develop slowly
over time.
Over the years, the interpretation given to major structural defect by this Tribunal has
further restricted the warranty protection. In McGlade, the Vice-Chair also provided a
helpful review of the case law on the issue, some of which follows:
Robert & Donna Simmie (CRAT 1997):
In this case there was a major structural defect claim regarding the interior, load bearing
footing. The Tribunal found that cracks, gaps and blemishes were annoying but did not
constitute a major structural defect, as they did not materially and adversely affect the use
of the building.
David and Beverly Buss (CRAT 1998)
In this case it was held that a prospective fear couldn.t be adjudicated upon by the
Tribunal. Instead the Tribunal must look at the existing condition of the property not its
future condition.
* (Already cited by the respondent)
Mark and Lynne Allan (CRAT 1999)
This case reiterates that the onus is on the homeowner to validate the claim for major
structural defect. It states, on page 6: .in the case of Galoko (CRAT 1994) this Tribunal
considered what would amount to a major structural defect. .Major. was compared to
.minor. and the conclusion was that the defect must be one that renders a home virtually
uninhabitable, uncomfortable beyond reason, unsafe or in a state of imminent collapse..
As noted in the Buss decision, referenced above, this Tribunal has further held that such
defects in structure must be present at the time of the claim. In the 2003 decision of
Mazza, the Tribunal rejected the Applicant.s claim, finding that the case for structural
failure was speculative since the cracked basement and foundation walls posed only a
possible future threat to the structural integrity of the home in question, avoidable were
preventive repairs undertaken. The Tribunal quoted an earlier decision of Ban (LAT 2002)
as follows:
The case law is quite clear as regards major structural defect. As stated in the Richards
case it needs to be a threat to the structural integrity of the home and not a failure to repair
a defect, which could lead to further deterioration, or a more serious defect in the future.
THE LAW:
The Ontario New Home Warranties Plan Act states:
Section 4.(1):
Each person with a claim under the Plan shall give written notice of the claim to the
Corporation.
Section 13 of the Act states:
(1) Every vendor of a home warrants to the owner,
(a) that the home
(i) is constructed in a workmanlike manner and is free from defects in material.
(ii) is fit for habitation, and
(iii) is constructed in accordance with the Ontario Building Code.
(b) that the home is free of major structural defects as defined by the regulations; and
(c) such other warranties as are prescribed by the regulations.
(2) A warranty under subsection (1) does not apply in respect of,
(a) defects in materials, design, and work supplied by the owner;
(b) secondary damage caused by defects, such as property damage and personal
injury;
(c) normal wear and tear;
(d) normal shrinkage of materials caused by drying after construction;
(e) damage caused by dampness or condensation due to failure by the owner to
maintain adequate ventilation;
(f) damage resulting from improper maintenance;
(g) alterations, deletions or additions made by the owner;
(h) subsidence of the land around the building or along utility lines, other than
subsidence beneath the footings of the building;
(i) damage resulting from an act of God;
(j) damage caused by insects and rodents, except where construction is in
contravention of the Ontario Building Code;
(k) damage caused by municipal services or other utilities
(l) surface defects in work and materials specified and accepted in writing by the
owner at the date of possession.
(3) the vendor of a home shall deliver to the owner a certificate specifying the date upon
which the home is completed for the owner s possession and the warranties take
effect from the date specified in the certificate.
(4) A warranty under subsection (1) applies only in respect of claims made hereunder
within one year after the warranty takes effect, or such longer time under such
conditions as are prescribed.
(5) A warranty is enforceable even though there is no privity of contract between the
owner and the vendor.
(6) The warranties set out in subsection (1) apply despite any agreement or waiver to the
contrary and are in addition to any other rights the owner may have and to any other
warranty agreed upon.
Section 14 of the Act states:
(1) Subject to the regulations, a person who has entered into a contract to purchase a
home from a vendor is entitled to receive payment out of the guarantee fund for the
amount that the person paid to the vendor as a deposit to be credited to the purchase
price under the contract on closing if,
(a) the person has exercised a statutory right to rescind the contract before closing; or
(b) the person has a cause of action against the vendor resulting from the fact that title
to the home has not been transferred to the person because,
(i) the vendor has gone into bankruptcy, or
(ii) the vendor has fundamentally breached the contract
(2) Subject to the regulations, an owner of land who has entered into a contract with a
builder for the construction of a home on the land and who has a cause of action
against the builder for damages resulting from the builder.s failure to substantially
perform the contract, is entitled to receive payment out of the guarantee fund of the
amount by which the amount paid by the owner to the builder under the contract
exceeds the value of the work and materials supplied to the owner under the contract.
(3) Subject to the regulations, an owner of a home is entitled to receive payment out of the
guarantee fund for damages resulting from a breach of warranty if,
(a) the person became the owner of the home through receiving a transfer of title to it
or through the substantial performance by a builder of a contract to construct the home
on land owned by the person; and
(b) the person has a cause of action against the vendor or the builder, as the case may
be, for damages resulting from the breach of warranty
(4) Subject to the regulations, an owner who suffers damage because of a major structural
defect mentioned in clause 13 (1) (b) is entitled to receive payment out of the guarantee
fund for the cost of the remedial work required to correct the major structural defect if the
owner makes a claim within four years after the warranty expires or such longer time
under such conditions as are prescribed.
(5) For the purposes of this section, a contract is substantially performed if it is substantially
performed within the meaning given by subsection 2 (1) of the Construction Lien Act (6)
In assessing the amount for which a person is entitled to receive payment out of the
guarantee fund under this section, the Corporation shall take into consideration any
benefit, compensation, indemnity payable, or the value of work and materials furnished
to the person from any source
(7) The Corporation may perform or arrange for the performance of any work in lieu of or in
mitigation of damages claimed under this section.
Section 16 of the Act states:
(1) Where the Corporation makes a decision under section 14, it shall serve notice of the
decision, together with written reasons therefor, on the person or owner affected.
(2) A notice under subsection (1) shall state that the person or owner served is entitled to a
hearing by the Tribunal if the person or owner mails or delivers, within fifteen days after
service of the notice under subsection (1), notice in writing requiring a hearing to the
Corporation and the Tribunal.
(3) Where a person or owner gives notice in accordance with subsection (2), the Tribunal
shall appoint a time for and hold the hearing and may by order direct the Corporation to
take such action as the Tribunal considers the Corporation ought to take in accordance
with this Act and the regulations, and for such purposes the Tribunal may substitute its
opinion for that of the Corporation.
(4) The Corporation, the person or owner who has required the hearing and such other
persons as the Tribunal may specify are parties to proceedings before the Tribunal under
this section.
Regulation 892, Section 1 states:
“major structural defect means for the purposes of clause 13 (1)(b) of the Act, any defect in
work or materials,
(a) that results in failure of the load-bearing portion of any building or materially and
adversely affects its load-bearing function, or
(b) that materially and adversely affects the use of such building for the purpose for
which it was intended.
including significant damage due to soil movement, major cracks in basement walls,
collapse or serious distortion of joints or roof structure and chemical failure of
materials, but excluding flood damage, dampness not arising from failure of a loadbearing
portion of the building, damage to drains or services, damage to finishes
and damage arising from acts of God, acts of the owners and their tenants,
licensees and invitees, acts of civil and military authorities, acts of war, riot,
insurrection or civil commotion and malicious damage.
Section 16 of Regulation 892 states:
16.Where a home was enrolled after the 31st day of December, 1990, the claim for
damages because of a major structural defect may be made within seven years of the
date specified in the certificate of completion and possession.
APPLICATION OF LAW TO FACTS FOUND PROVEN:
What is the proper definition of .major structural defect. in the current case? In our
opinion, a major structural defect should be one that renders a home virtually
uninhabitable, uncomfortable beyond reason, unsafe or in a state of imminent collapse.
There is absolutely no evidence in the present case that has been presented from the
Applicants to substantiate such a claim. To the contrary, from their own admission they
have occupied their house fully since the date of possession in 1998.
The Tribunal has a great deal of sympathy for the Applicants with the problems they have
encountered with their home. The Tribunal fully realizes that the purchase of a home is,
for the majority of the people living in Ontario, the biggest investment of their lives and the
majority also take 20 years or more to pay off their mortgage.
Having said that the Tribunal must look at the entire evidence and try to understand what
happened in the present case.
The Applicants filed a claim with Tarion and a decision letter was issued on February 08,
2001. An appeal was filed by them and a hearing took place on September 25 and 28,
2001. In his decision Vice-Chair Douglas Macintosh wrote that over 100 complaints were
addressed in two different conciliation reports. Tarion found that 46 complaints were
warranted and 61 were not warranted. Cory Beverdam, the Program s warranty
representative, who has wide experience in house construction, prepared the reports.
They were awarded $ 12,455.00 compensation by the Tribunal at that time.
That raises the next question for the Tribunal why the Applicants waited within the final
week of the 7-year warranty period to file a claim.
They knew at least since 2003 of their structural problems and they waited two more years
before notifying Tarion. The Applicants had in their possession a report by an engineering
firm that told them there were problems.
In the eyes of the Tribunal there exists the notion of a duty to fix and maintain your
property. The Applicants did not notify Tarion. Why? Was it because it was just annoying
and it had no effect on the use of the home? We do not know.
There is absolutely nothing wrong with the second floor. No evidence was presented that
there were major problems in the garage either.
From the evidence presented there has been no change in the structural situation
between the first and the second reports of the engineer Mr. Higginson.
The dwelling is stable. Nothing imminent is on the horizon.
CONCLUSION:
In many hearings before the Tribunal, the applicants do not understand what the
requirements are for their claim to qualify as a .major structural defect..
The burden of proof lies with the Applicants in the present case, and the onus is on the
Applicants to satisfy the Tribunal that the complaints are filed pursuant to the relevant
section of the Act. By their own admission, (report of their expert) only the first five items
are classified as major structural defects, hence, items 6 to 12 were not presented as such
and are therefore rejected. (9,10 and 12 were already withdrawn at the beginning of the
hearing) Of the first five items none qualifies as a major structural defect.
The warranty provided by the legislation does not support the current claims. The warranty
purports to provide remedies to those owners who are frustrated in their actual ability to
substantially make use of the home or who have major problems that the building is
structurally at risk. Such has not been established by the evidence here.
DECISION:
Pursuant to the authority vested in it by section 16. (3) of the Ontario New Home
Warranties Plan Act, the Tribunal directs Tarion Warranty Corporation to disallow the
Applicants claims.
LICENCE APPEAL TRIBUNAL
______________________
Daniel Laurin, Vice-Chair
RELEASED: August 16, 2006
File name: 3409.nhw.fuller.swick
The decision will also be available on Quicklaw at a later date.