Results can be costly if contract is not specific
An Ontario Superior Court decision released earlier this year provides a textbook example of how and how not to prepare a home renovation contract.
Maureen Chung and Geoffrey Jackson operate a renovation business in the Toronto area. In early 2004, they were hired to renovate the kitchen in the Thornhill home of Arik and Olga Idan.
Detailed discussions took place outlining the work the Idans wanted done in their home, and ultimately a contract was signed which outlined only the bare essentials of the work to be completed and the price of $28,000.
What was intended to be a renovation of “about 8 weeks” dragged on through the summer of 2004 until the Idans ultimately called a halt to the job. By this time they had paid more than $32,000 for the renovations, but Chung and Jackson wanted another $19,200 for 35 extras they claimed were not included in the contract price.
Unfortunately, it seems that the brief renovation contract omitted more details than it included, and it wasn’t long before both parties were suing each other. The renovators sued the Idans for the $19,200 in extras, and the Idans counterclaimed for $50,000 in damages to repair what they claimed was faulty work.
An eight-day trial of the action was held before Justice Paul Perell earlier this year. In his ruling, the judge wrote, “In my opinion, the events that took place between January and August 2004 at the Idans’ home provide an illustration of many, if not all, of the major mistakes and misadventures that can occur during a home renovation and also they are an illustration of the causes of those mistakes and misadventures.”
Much of the evidence at trial consisted of claims by both sides on what verbal agreements were, or were not, intended to be included in the contract price. All the conflicting testimony prompted Justice Perell in his decision to quote the film producer Samuel Goldwyn’s famous quip, “An oral contract isn’t worth the paper it’s written on.”
He added that the events described in the evidence indicated to him that a fixed-price renovation contract should be in writing and should at least:
In the end, Justice Perell ruled that “the money the Idans spent on this renovation project was wasted. … I conclude that the goods and services provided by Ms. Chung and Mr. Jackson are worthless.”
He denied their demand for $19,200 and awarded the Idans the full $50,000 they requested in damages to remove the work already done and “secure the structural integrity of the house.”
In a subsequent ruling in March of this year, the judge awarded the Idans an additional $1,650 in interest and $41,731 in legal costs.
In the end, the renovators not only lost their court case, but wound up having to pay the Idans more than $93,000 and their own lawyer’s bill.
Before his appointment as a judge, Justice Perell was an accomplished real estate lawyer and author. He taught real estate law at Osgoode Hall Law School and the now-defunct Bar Admission Course, and was the recipient of many awards including the Law Society Medal.
His decision in the Chung and Idan litigation is a classic example of his superb skills as an author and teacher, since it provides a checklist of the minimum requirements necessary for a home renovation contract. In future, homeowners and renovators who ignore Justice Perell’s lessons in this case do so at their own risk.